Roadmap

The deliverable released in the 1st Phase of the SAPIENT Project have been marked in light blue.

 

 

WP 1

01/04/2016 – 29/09/2017 Project Management
·         Coordination of all activities (management and technical)

·         Ensure harmonization of the tasks in respect of the objectives and the schedule

·         Management of the contractual and administrative aspects of the project

Deliverables
29/09/2017 D1.1 Executive summary
29/04/2016 D1.2 Project Management Plan

 

 

WP2

01/04/2016 – 31/05/2016 Initial definition of SAPIENT objectives and target benefits
·         Definition of the intended objectives of the SAPIENT System

·         Provision the initial estimate of its achievable benefits

Deliverables
31/05/2016 D2.1 SAPIENT System objectives and target benefits

 

WP3

01/04/2016 – 31/08/2017 Evaluation of SAPIENT results and benefits assessment
Provision of a synthesis of the findings and apply it together with feedbacks gathered from dissemination to define the next steps of the SAPIENT design roadmap
Deliverables
31/08/2017 D3.1 Evaluation of SAPIENT results and benefits assessment

 

WP4

02/05/2016 – 31/08/2017 Definition of Terrestrial DL KPIs and Measurement and Processing Requirements
·         Definition the KPIs of terrestrial L band DL and harmonise them with those of satellite DL

·         Definition of a unified set of KPIs, define the functional, performance and verification requirements for Measurement and processing of terrestrial DL-KPIs

·         Allocation of the Measurement and Processing requirements to terrestrial L band DL segments

Deliverables
29/09/2016 D4.1 Terrestrial and Satellite DL KPIs and Requirements for Measurement and Processing Issue 1
31/08/2017 D4.2 Terrestrial and Satellite DL KPIs and Requirements for Measurement and Processing Issue 2

 

WP5

02/05/2016 – 31/08/2017 Definition of Satcom DL KPIs and Measurement and Processing Requirements
·         Definition of the KPIs of satcom DL and Contribution to their harmonisation with those of terrestrial L band DL

·         Definition of functional, performance and verification requirements of Measurement and Processing of satcom DLKPI

·         Allocation of the Measurement and Processing requirements to satcom DL segments

Deliverables
29/09/2016 D5.1 Contribution to “Terrestrial and Satellite DL KPIs and Requirements for Measurement and Processing Issue 1″
31/08/2017 D5.2 Contribution to “Terrestrial and Satellite DL KPIs and Requirements for Measurement and Processing Issue 2”

 

WP6

01/08/2016 – 30/01/2017 Definition of KPI 4D Tagging and 4D-MAP protocols
Definition of the SAPIENT KPI 4D Tagging and the 4D-MAP (Monitoring of Aerocom DL Performance) protocols
Deliverables
27/01/2017 D6.1 Definition of KPI 4D Tagging and 4D-MAP protocols

 

WP7

01/08/2016 – 27/01/2017 SAPIENT Security architecture
·         Definition of the threats to SAPIENT System

·         Assessment of the associated risks and severity

·         Definition of the SAPIENT security architecture in terms of functional, performance and verification requirements

Deliverables
27/01/2017 D7.1 SAPIENT System threat analysis and security architecture

 

WP8

01/08/2016 – 31/07/2017 SAPIENT System Architecture
·         Design of the SAPIENT functional and protocol architecture

·         Definition of the SAPIENT performance, security and verification requirements for the airborne, ground and satellite segments, including the relevant inter-segment interfaces

·         Definition of  protocol, performance, security and verification requirements for the external interfaces of SAPIENT System

Deliverables
31/07/2017 D8.1 SAPIENT System functional architecture design and justification
31/07/2017 D8.2 SAPIENT System external and internal interfaces requirement definition and justification

 

WP9

02/05/2016 – 31/07/2017 SAPIENT System models and performance
·         Definition of the relevant/significant features and scenarios of the SAPIENT System as input to definition of SAPIENT System simulation requirements and

·         Definition of the architecture of the SAPIENT simulator

·         Building the SAPIENT simulator, including models of communication elements and communication links, possibly exploiting already available libraries, SW modules etc.

·         Definition of the SAPIENT System simulation plan and simulation procedures

·         Execution of the SAPIENT simulations to assess the performance of the SAPIENT System, support the major trade-off choices, determine achievable performance and identifying and solving scalability issues, bottlenecks and vulnerabilities

Deliverables
30/09/2016 D9.1 SAPIENT simulator requirements
31/05/2017 D9.2 SAPIENT simulator architecture design and justification
31/07/2017 D9.3 SAPIENT simulation plan and procedures
31/07/2017 D9.4 SAPIENT Simulator execution report and resulting SAPIENT performance

 

WP10

01/04/2016 – 29/09/2017 Dissemination and Exploitation plan
This WP will run throughout the project life-time and will address the coordination of the dissemination and exploitation actions, their planning, monitoring and reporting. The main objectives of this WP are:

·         To coordinate the dissemination actions, their planning, monitoring and reporting

·         To identify target-groups with immediate or potential interest in the topic of the project (service providers, end-users, stakeholders, transportation companies, MS authorities)

·         To ensure that the project results translate into enhanced understanding of the potential offered by SAPIENT research.

Deliverables
31/05/2017 D10.1 SAPIENT Dissemination and Promotion Plan
29/07/2016 D10.2 SAPIENT Project Website
31/08/2017 D10.3 SAPIENT user community Dissemination outcomes

 

WP11

01/04/2016 – 29/09/2017 Ethics requirements
Ensure compliance with the ‘ethics requirements’ set out in this work package.
Deliverables
29/04/2016 D11.1 POPD – Requirement No.2
29/04/2016 D11.2 M – Requirement No.1
29/04/2016 D11.3 POPD – Requirement No.5
29/04/2016 D11.4 DU – Requirement No.4